Forestry and Agriculture

CKPI Installation of Chip Thickness Screening System

Client / Owner

Canadian Kraft Paper Industries Ltd.
Time and Material.

Location
Completion Date
July 2019
No items found.

CKPI Installation of Chip Thickness Screening System

Canadian Kraft Paper Industries (CKPI) employed Raumaster Oy, located in Rauma, Finland, for the engineering and supply of a Chip Thickness Screening (CTS) system to remove contaminants from the mill’s chip supply. 

A new building located to the East side of the chip pile beside the C2 conveyor (to Digesters) was engineered by KGS Group to house the screening equipment and auxiliary systems. Two new conveyor assemblies will be tied into the existing chip handling conveyor systems to transport chips to and from the screening equipment. The CTS equipment, equipment support steel and two new conveyor assemblies were delivered and stored on-site in sea-can containers and their stores’ compound. The civil installation was completed in the fall of 2018 (with the exception of the building floor slab), which allowed for the erection of the equipment support steel, conveyors and building to begin prior to thaw in the spring. The E&I scope for this project was covered by in-house resources. The installation of the fire protection system was sourced by CKPI. TESC was engaged for the mechanical and structural installation of the Chip Thickness Screening system and associated building in The Pas, Manitoba.

TESC was responsible for supplying cranes and overseeing the coordination between multiple trades and subcontractors. With proper planning and by maintaining frequent communication with the engineer and the client, the TESC team managed to overcome minor challenges that have surfaced throughout the project, such as delay of steel to site, weather and succeeded with upholding the schedule. The work was executed alongside a shutdown in the existing facility.

The project was successfully completed on time, under budget and with no recordable injuries.

More Projects

Barrick Hemlo Cyanide Detox Plant & Tailings Flotation Complex
Glencore Onaping Depth Project Headworks Steel Installation
Domtar Power Recovery Boiler Chemical Treatment
Domtar HD Tower Piping
Coniston Generating Station 22kV-44kV Conversion
Mistinikon Lake Replacement of Spillway Guardrails and Flashboards
McVittie Generating Station Roof Replacement
Detour Gold Corporation Detour Lake Mine 13.8kV Substation Installation
Northgate Minerals Young Davidson Mine Substation Installation
BHP Billiton Jansen Mine Freeze Plant Supply Installation
Detour Gold Corporation Detour Lake Mine Concrete Slabs
Northgate Minerals Young Davidson Mine Headframe Construction
BHP Billiton Jansen Mine Hoist House Buildings
Vale No.8 Converter Installation
Sudbury INO Process Gas Project, Phase I
Mosaic K3 Mine Service Shaft Headframe Construction
Vale No.10 Converter Installation
Vale Matte Sep SMPEI Phase 2
Vale Matte Sep SMPEI Phase 1
Harte Gold Sugar Zone Mill Installation SMPEI Project
Tahoe Bell Creek Shaft Sinking Project
Sudbury Lime Plant Electrical Services Installation
Glencore Concentrate Unloading

Our portfolio

Project highlights showcasing TESC’s capabilities, problem solving, and leadership across industries.